New Photos
Fall-Winter, 2008
Status: December 5, 2008
Steam Operations Corporation, Muscle Shoals, AL: For the first time the new cylinder-saddle has been mated up with the frame, and it fits perfectly. This is only a test fit, and there is more machining to be done, but this is a real milestone!!
Photo: Steam Operations Corporation
Preparing for this step, the frame was leveled and all the binders installed. While still on the horizontal milling machine, "spiders" were precisely located in the centers of each of the bores. Using a 40 ton overhead crane, the cylinders were moved and slowly lowered onto the frame. It was a prefect fit and pulls up tight on the frame rails. (The fit is better than the original cylinders.)
This is a test fit. The cylinder-saddle will make several more trips between the milling machine and the frame before final assembly. Currently, the bores are all rough bored and long, but are on the correct centerlines. This test fit is a critical step to determine precisely the distance to the centerline of the main driver axle. Knowing this dimension, as well as the lengths of the main rod, crosshead & piston rod will allow the machinists to determine how much additional material will be removed from the pads to ensure the cylinders are correctly positioned on the frame.
These photos show Ronnie Jones, Tyler Poss and Craig moving the cylinder-saddle into position. (Click the photo for an enlarged view.)
Photos: Steam Operations Corporation
Status: November 24, 2008
Boiler work in Steele, AL is progressing well. Pretty much all that remains as of Nov 24 is installation of the tubes & flues. We're not in a particular hurry to complete this task as it's ahead of the cylinder & frame work going on in Muscle Shoals, AL. It would be nice if everything got completed at about the some time so the boiler could be fitted to the frame "just in time". Well, we'll do the best we can with this old machinery and various project competing for shop time.!
The tires have been delivered to TVRM in Chattanooga. They look great & and are awaiting the opportunity to shrink them on to the driver centers. After that, the crank pins will be quartered and then the completed drivers will be delivered to Muscle Shoals to be integrated with the frame.
In Muscle Shoals, work on machining the cylinder-saddle is progressing well. There have been the usual delays, but no serious problems. The driver bearing boxes were delivered in late Summer. After cleaning them up, it was discovered that the boxes are not in very good shape and will have to be replaced. Casting new driver boxes is not overly complex, but it is costly and was not anticipated. But, it has to be done and will be worked into the schedule & budget. (A 786 fund raiser is being planned to raise the balance of funds needed to complete the 786 project.)
New photos of the machining progress is shown below.
The Air Compressor and Cold Water pump restoration has been completed and delivered back to Austin. The work was done by Bernie Watts, a long time friend of ASTA, Backshop Enterprises in Wheat Ridge, Colorado (near Denver). (photos coming soon!)
Boiler Restoration & Repair
(Updated 11/24/2008)
The firebox area is complete. A few new stay bolts need to be installed, but all the hard tasks have been done. The dry pipe has been re-installed, attached to the super heater header, and hydro tested. The connections on the superheater header have all be cleaned up and are ready for mating to the super heaters (later). The tubes & flues will need to be installed next.
The bottom of the smoke box will be fabricated in Muscle Shoals and welded to the smoke box when the boiler & frame are mated up in Muscle Shoals some time in 2009.
Cylinder-Saddle Machining &
fitting
(Updated Nov 24, 2008)
New Photos
Spring - Summer, 2008
Boiler Restoration & Repair
(Updated Sept 6, 2008)
After several surprises (that happens a lot with old machinery!) and extensive work in the firebox area, work on the boiler had gotten ahead of the cylinder machining. So, when another boiler project came along, we agreed to temporarily suspend work on 786's boiler for 5-6 months. Now, Historic Machinery (Bob Yuill) has just resumed work on the boiler - there is still plenty to do!
There will be more boiler progress photos in the coming months.
Mounting & Machining
Cylinder-Saddle Surface
(Updated Sept 3, 2008)
July & August will be active months of machining for 786's cylinder castings. The bottom of the cylinders has been machined to fit on the frame. A special machining fixture has been made to hold the cylinders in position for machining on the big horizontal boring mill. The cylinders are mounted on the fixture and aligned with the mill.
The next machining step is to cut the 3.5 foot radius that forms the base for the bottom of the boiler's smoke box.
By the time the cylinder castings have been completely machined and mounted on the frame, approximately 4,000 pounds of chips will have been removed!
Cylinder-Saddle and Running
Gear
(Updated July 8, 2008)
In April. 2008, volunteers Bill Nash & John Mandell delivered about 8,000 pounds of 786 components to Steam Operations Corporation in Muscle Shoals, AL.
The machining of the cylinder-saddle is progressing well as you can see from these photos.
Webmaster:
jmandell2@pointech.com